FY 27 Proposed Capital Budget
Drainage Improvements
HIGHWAYS - ROADS Project Number:
Expended/Encumbered as of 2/3/26: $1,953,961
H064506 Multiple Various
Council District:
Location:
Project Schedule/Status: This is an ongoing program. Various projects are continually being designed and constructed under this account.
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides for the design and construction of various solutions to address drainage problems throughout the County. Additionally, funds are included to address sump pump discharges onto County roads. These discharges create icing problems in the winter and are a continuing maintenance concern.
This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
195,000 22,250
20,000
215,000 22,250
20,000
20,000
20,000
20,000
20,000
315,000 22,250
Construction
2,055,000 120,000 2,175,000 120,000 120,000 120,000 120,000 120,000
2,775,000
Inspection Fees
152,750
10,000
162,750
10,000
10,000
10,000
10,000
10,000
212,750
Equipment/Furnishing
0
0
Total Cost:
2,425,000 150,000 2,575,000 150,000 150,000 150,000 150,000 150,000
3,325,000
FUNDING SCHEDULE
R8750 Paygo R7100 Prior Bonds
2,225,000 150,000 2,375,000 150,000 150,000 150,000 150,000 150,000
3,125,000
200,000
200,000
200,000
0 0 0
0 0 0
Total Cost:
2,425,000 150,000 2,575,000 150,000 150,000 150,000 150,000 150,000
3,325,000
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL 35,070
6,680
6,346
6,012
5,678
5,344
5,010