FY 27 Proposed Capital Budget
Fleet Replacement
HIGHWAYS - MISCELLANEOUS Project Number: H124507 Council District: Multiple Location: Various Project Schedule/Status:
Expended/Encumbered as of 2/3/26: $31,585,028
This project will be managed/controlled by the Department of Procurement, Fleet Management Division.
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides funds for the replacement of essential vehicles and equipment to enable using agencies to perform their critical jobs. We are behind in consistent rotation which has caused maintenance costs to rise, fuel inefficiency, and fleet availability to plummet. Units to be replaced are on average 10 years old with high mileage and have become unreliable.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
32,992,000 4,500,000 37,492,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 62,492,000 32,992,000 4,500,000 37,492,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 62,492,000
Total Cost:
FUNDING SCHEDULE R8750 Paygo R6130 Investment Inc R7000 Future Bonds
30,292,000 2,700,000
30,292,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 55,292,000
2,700,000
2,700,000 4,500,000
4,500,000 4,500,000
0 0
0
0 32,992,000 4,500,000 37,492,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 62,492,000
Total Cost:
ESTIMATED OPERATING BUDGET IMPACT:
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
$150,300 $142,785 $135,270 $127,755 $120,240 $112,725
$789,075