FY 27 Proposed Capital Budget
Abingdon Water Treatment Plant Facility Improvements
WATER Project Number: Council District:
Expended/Encumbered $0
NEW
Multiple Abingdon
Location:
Project Schedule/Status: FY27 - 29 Filter bed upgrade and media replacement
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project will provide for studies, design, and construction of various process equipment, facilities, buildings, and electrical equipment. Projects will extend the useful life of the facility and support permit compliance. Anticipated project work includes improvements to the existing filters and replacement of filter media.
EXPENDITURE SCHEDULE
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Cost Element
Prior
FY 2027 Approp Total
Engineering/Design Land Acquisition
100,000
100,000
50,000
50,000
50,000
50,000
50,000
350,000
0
0
Construction
500,000
500,000 500,000 500,000 500,000 500,000 500,000
3,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
0 600,000
600,000 550,000 550,000 550,000 550,000 550,000
3,350,000
FUNDING SCHEDULE
600,000
600,000 550,000 550,000 550,000 550,000 550,000
3,350,000
R8750 Paygo
0 0 0 0
0 0 0 0
Total Cost:
0 600,000
600,000 550,000 550,000 550,000 550,000 550,000
3,350,000
ESTIMATED OPERATING BUDGET IMPACT: