FY 27 Proposed Capital Budget
Fleet Maintenance Facility
WATER & SEWER MISCELLANEOUS Project Number: O186037 Council District: C Location: Hickory Project Schedule/Status:
Expended/Encumbered as of 2/3/26: $1,174,502
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides for engineering, design and construction of a new Fleet Maintenance/Radio Shop facility for Harford County and the Board of Education. The facility was listed as a high priority in the Countywide Facilities Master Plan Study.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2027 FY 2028 FY 2029 FY 2030 FY 2031
TOTAL
Engineering/Design Land Acquisition
140,000
140,000
140,000
0
0
Construction
1,280,000
1,280,000
1,280,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
1,420,000
0 1,420,000
0
0
0
0
0
1,420,000
FUNDING SCHEDULE
R7100 Prior Bonds
1,420,000
1,420,000
1,420,000
0 0 0 0
0 0 0 0
Total Cost:
1,420,000
0 1,420,000
0
0
0
0
0
1,420,000
ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service
FY 2027 TOTAL 47,428 45,057 42,685 40,314 37,942 35,571 248,997 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032