FY 27 Proposed Capital Budget

Courthouse Building Repairs

GENERAL Project Number: Council District:

Expended/Encumbered as of 2/3/26 $10,228,906

A094102

C

Location:

Bel Air

Project Schedule/Status: FY 27: Courthouse restrooms

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project provides funds for the replacement, renovation and repairs of courthouse building systems (site, roofing, structural, exterior, interior, mechanical, plumbing, electrical, fire/life safety, and conveyances).

EXPENDITURE SCHEDULE

FY 2028 FY 2029 FY 2030 FY 2031 FY 2032

TOTAL

Cost Element

Prior

FY 2027 Approp Total

Engineering/Design Land Acquisition

1,035,000

1,035,000

1,035,000

0

0

Construction

8,999,900 350,000

9,349,900

9,349,900

Inspection Fees

300,000

300,000

300,000

Equipment/Furnishing

0

0

Total Cost:

10,334,900 350,000 10,684,900

0

0

0

0

0 10,684,900

FUNDING SCHEDULE

R3150 Federal ARRA R8750 Paygo R7100 Prior Bonds

134,900

134,900 450,000

134,900 450,000

100,000 350,000

10,100,000

10,100,000

10,100,000

Total Cost:

10,334,900 350,000 10,684,900

0

0

0

0

0 10,684,900

ESTIMATED OPERATING BUDGET IMPACT: Estimated Debt Service

FY 2026 337,340

FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 320,473 303,606 286,739 269,872 253,005

TOTAL

1,771,035