FY 27 Proposed Capital Budget
Facilities Repair Program/Life-Cycle Program
GENERAL Project Number: Council District:
Expended/Encumbered as of 2/3/26: $5,436,997
A234105 Multiple
Location: Various Project Schedule/Status: N/A
Expended/Enc.
Budget
PROJECT DESCRIPTION:
This project provides funding for the systematic replacement, renovation, and repairs of critical County building systems to esure the continued safety, functionality, and efficiency of public facilities. Improvements may include site, roofing, structural, building envelope, mechanical, plumbing, electrical, fire and life safety systems, and conveyances. These investments are essential to extend the useful life of County assets, maintain regulatory compliance and provide safe, reliable enviroments for employees and the public. Proactive reinvestment in these systems also reduces the risk of costly emergency repairs, minimizes service disruptions, and supports the County's long term fiscal responsibility by avoiding the expense of deferred maintenance.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
2,360,000 500,000 2,860,000 200,000 200,000 200,000 200,000 200,000
3,860,000
0
0
Construction
7,340,460 4,500,000 11,840,460 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 20,840,460
Inspection Fees
0 0
0
Equipment/Furnishing
0 9,700,460 5,000,000 14,700,460 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 24,700,460
Total Cost:
FUNDING SCHEDULE
R7000 Future Bonds R7100 Prior Bonds R3199 Federal Other
5,000,000 5,000,000 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 15,000,000
9,500,460
9,500,460
9,500,460
200,000
200,000
200,000
0 0
0
0 9,700,460 5,000,000 14,700,460 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 24,700,460
Total Cost:
Debt Service ESTIMATED OPERATING BUDGET IMPACT:
FY 2027 484,315
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 460,100 435,884 411,668 387,452 363,237
TOTAL
2,542,656