FY 27 Proposed Capital Budget
HCSO Fleet Replacement
PUBLIC SAFETY Project Number: Council District:
Expended/Encumbered as of 2/3/26: $7,841,971
E224109 Multiple Various
Location:
Project Schedule/Status:
This project is ongoing.
Expended/Enc.
Budget
PROJECT DESCRIPTION: The Sheriff's Office operates a fleet of over 400 vehicles. This funding provides for the annual replacement of approximately 8% of the HCSO fleet.
FY 27 - replace 30 police vehicles and 2 utility vehicles per County Fleet guidelines
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
8,780,000 1,500,000 10,280,000 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 17,280,000 8,780,000 1,500,000 10,280,000 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 17,280,000
Total Cost:
FUNDING SCHEDULE R8095 Reapp Interest R6130 Invest Income R3199 Federal Other R8750 Paygo R8089 Reapp Paygo
0 0 5,780,000 1,500,000 7,280,000 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 14,280,000 1,599,151 1,599,151 1,599,151 1,063,167 1,063,167 1,063,167 337,682 337,682 337,682 8,780,000 1,500,000 10,280,000 1,400,000 1,400,000 1,400,000 1,400,000 1,400,000 17,280,000
Total Cost:
ESTIMATED OPERATING BUDGET IMPACT: Equipment for Vehicles
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
5,692,596
1,000,896 938,340 938,340 938,340 938,340 938,340
95