Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
George D. Lisby HVAC Systemic Renovation
Project Number: Council District:
Operating Budget Impact
B204110
E
Revenues:
Location:
Aberdeen
Expenditures: Cost Savings: None:
Est. Debt Service:
$96,800 (annual)
X
Expended/Encumbered as of 1/9/23: $9,250,000
Project Schedule/Status: Complete
PROJECT DESCRIPTION: This project addresses the replacement of the HVAC system for the entire facility. It will also replace the exterior windows and doors that date back to the original construction. A back-up generator will be added to address lief safety requirements and meet HCPS design standards, any additional requirements for compliance with MEMA if needed, will be incorporated. A new HVAC system will provide comfort, humidity control, greater energy efficiency and centralized systems controls.
Prior Bonds have been reallocated to HCPS Site Improvements @ $19,563
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
700,000
700,000
700,000
0
0
Construction
8,400,000
(19,563)
8,380,437
8,380,437
Inspection Fees
150,000
150,000
150,000
Equipment/Furnishing
0
0
Total Cost:
9,250,000
(19,563)
9,230,437
0
0
0
0
0
9,230,437
FUNDING SCHEDULE
R7920 State Bonds R7100 Prior Bonds
4,410,000 4,840,000
4,410,000 4,820,437
4,410,000 4,820,437
(19,563)
0 0 0
0 0 0
Total Cost:
9,250,000
(19,563)
9,230,437
0
0
0
0
0
9,230,437