Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program

Healthy School Facility Fund - Local Match

BOARD OF EDUCATION Project Number: New Council District: D Location:

Operating Budget Impact Revenues:

Pylesville

Expenditures: Cost Savings: None:

Est. Debt Service:

$25,200 (annual)

Expended/Encumbered as of 1/9/23: $0

Project Schedule/Status: Design: Summer/fall 2023 Bid: Spring of 2024 Construction: Begin summer 2024 and completed by fall

PROJECT DESCRIPTION: Health School Facility Fund is to provide grants to public schools for capital projects that will improve the health of school facilities. This includes projects that will improve the conditions related to air conditioning, heating, indoor air quality, mold remediation, temperature regulation, plumbing including the presence of lead in drinking water outlets, roofs, and windows. All approved projects have a local match requirement, based on the State-local cost share percentage applicable to projects approved in the Capital Improvement Program. The LEA is required to have local funds available for the payment of cost in excess of the State allocation and ineligible project cost. In FY 23, the IAC changed the submission timeline so it no longer aligns with the CIP timeline. In order for HCPS to take advantage of the State funds, we must have an established local match funding prior to applying for the grant.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2024 Approp Total

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

300,000

300,000

300,000

0

0

Construction

2,944,000 2,944,000

2,944,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

0 3,244,000 3,244,000

0

0

0

0

0

3,244,000

FUNDING SCHEDULE

R7920 State Bonds R7000 Future Bonds R3399 State Other

0

0

1,200,000 1,200,000 2,044,000 2,044,000

1,200,000 2,044,000

0 0

0 0

Total Cost:

0 3,244,000 3,244,000

0

0

0

0

0

3,244,000