Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Emily Bayless Graham Park
PARKS AND RECREATION Project Number:
Operating Budget Impact
P124120
Council District:
B
Revenues:
Location:
Emmorton
Expenditures: Cost Savings: None:
Est. Debt Service:
N/A
(annual)
X
Expended/Encumbered as of 1/9/23: $2,007,293
Project Schedule/Status: FY 23: Stabilization and weatherization of the outbuildings. The farmhouse has been stabilized and weatherized.
PROJECT DESCRIPTION: Emily Bayless Graham Park will focus on passive park development for a site in Emmorton. In fulfillment of Mrs. Graham's wishes for the property, the park will include natural trails, picnic pavilions, and opportunities for the public to learn about the history of the site and the surrounding community. Preservation of this tract will provide critically needed public open space in the heart of the County's development envelope. Additional residential growth is anticipated in the area and will generate demand for parks. This project supports the goals and objectives of the 2018 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
495,000
495,000
495,000
0
0
Construction
2,840,000 250,000 3,090,000
750,000
3,840,000
Inspection Fees
60,000
60,000
60,000
Equipment/Furnishing
0
0
Total Cost:
3,395,000 250,000 3,645,000
0 750,000
0
0
0
4,395,000
FUNDING SCHEDULE
R6999 Other R8750 Paygo
1,275,000
1,275,000
500,000
1,775,000
150,000
150,000
150,000
R1515 Recordation Tax R3380 Prog. Open Sp.
1,047,500 250,000 1,297,500
250,000
1,547,500
922,500
922,500
922,500
0
0
Total Cost:
3,395,000 250,000 3,645,000
0 750,000
0
0
0
4,395,000