Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program

Vale Road Park

PARKS AND RECREATION Project Number:

Operating Budget Impact

P224117

Council District:

B

Revenues:

Location:

Bel Air

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 1/9/23: $124,645

Project Schedule/Status: Engineering is underway.

PROJECT DESCRIPTION: This project proposes the construction of new active recreation facilities on the northern side of Heavenly Waters Park. These facilities will address needs for the Bel Air community and will include soccer/lacrosse fields and related amenities. Future projects will include a storage building, picnic pavilion, and small playground. Population growth will generate demand for additional recreation facilities. This project supports the goals and objectives of the 2018 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2024 Approp Total

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

125,000 100,000

225,000

225,000

0

0

Construction

200,000

200,000 1,800,000

2,000,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

125,000 300,000

425,000 1,800,000

0

0

0

0

2,225,000

FUNDING SCHEDULE R1515 Recordation Tax R3380 Prog. Open Sp. R7000 Future Bonds

125,000 300,000

425,000 300,000

725,000 500,000

0 500,000 0 1,000,000

1,000,000

0 0

0 0

Total Cost:

125,000 300,000

425,000 1,800,000

0

0

0

0

2,225,000

234