Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Jarrettsville Recreation Complex/Center
PARKS AND RECREATION Project Number:
Operating Budget Impact
P154111
Council District:
D
Revenues:
Location:
Jarrettsville
Expenditures: Cost Savings: None:
Est. Debt Service:
$88,200 (annual)
X
Expended/Encumbered as of 1/9/23: $426,872
Project Schedule/Status: FY 23: Engineering/design for the recreation center. Construction of walking trail will occur in 2022.
PROJECT DESCRIPTION: This project will provide a multipurpose center to serve the leisure needs for all in the Jarrettsville community. The center will include a gymnasium, fitness room, and multipurpose rooms for a variety of community recreational programs. Future site amenities include a picnic pavilion and walking trails. This supports the goals and objectives of the 2018 Lane Preservation, Parks and Recreation Plan and its Capital Improvement Program recommendations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
1,710,775
1,710,775
150,000
1,860,775
0
0
Construction
3,000,000
3,000,000 1,000,000
4,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
4,710,775
0 4,710,775 1,000,000
0
0
0 150,000
5,860,775
FUNDING SCHEDULE R8750 Paygo R7000 Future Bonds R1515 Recordation Tax R7100 Prior Bonds R3380 Prog. Open Sp.
425,000
425,000
425,000
0 1,000,000
1,000,000
85,775
85,775
150,000
235,775
4,200,000
4,200,000
4,200,000
0
0
Total Cost:
4,710,775
0 4,710,775 1,000,000
0
0
0 150,000
5,860,775