Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Carrs Mill Road (MD 152-Grafton Shop Road)
HIGHWAYS - ROADS Project Number:
Operating Budget Impact
New
Council District:
B
Revenues:
Location:
Fallston
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 1/9/23: $0
Project Schedule/Status: FY 25: Design FY 26: Right of way Outyears: Construction
PROJECT DESCRIPTION: Carrs Mill Road between MD 152 and Grafton Shop Road is to be improved to adequately handle existing and projected traffic loads and to improve safety. The initial phase from MD 152 to Belle Meade Road is complete. Previous improvements include new guardrails and the removal of several large rock outcroppings directly adjacent to the roadway. Future improvements will include a widening and realigning of the roadway to improve the safety and a realignment of the intersection(s) of Vale Road and Carrs Mill Road. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
0 100,000
100,000 100,000
0 0 0 0
100,000
Construction
0 0 0
Inspection Fees
Equipment/Furnishing
Total Cost:
0
0
0 100,000 100,000
0
0
0
200,000
FUNDING SCHEDULE
R7000 Future Bonds
0 100,000 100,000
200,000
0 0 0 0
0 0 0 0
Total Cost:
0
0
0 100,000 100,000
0
0
0
200,000