Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Joppatowne Area Watershed Restoration
WATERSHED MANAGEMENT Project Number: New Council District: A Location:
Operating Budget Impact
Revenues:
Joppatowne
Expenditures: Cost Savings: None:
Est. Debt Service:
$6,300
(annual)
X
Expended/Encumbered as of 1/9/23: $0
Project Schedule/Status:
PROJECT DESCRIPTION: Sedimentation has been occurring in the tidal areas of Foster Branch and Rumsey Island requiring dredging for boating access. A watershed assessment was completed in Foster Branch in 2012. Assessments for Mariner Run (Rumsey Island sub watershed) and Rumsey Island are pending. The assessments provide prioritized recommendations for restoration projects, including stream restoration and stormwater management retrofit that provides the most cost effective improvements to water quality and reductions in sedimentation. Water quality restoration projects are required under the County's municipal NPDES or MS4 permit and through the Chesapeake Bay Watershed Implementation Plan as required under the Bay TMDL.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
300,000
300,000 400,000
400,000
1,100,000
0 0 0 0
0
Construction
855,000 45,000
855,000 855,000
2,565,000
Inspection Fees
45,000
45,000
135,000
Equipment/Furnishing
0
Total Cost:
0 300,000
300,000 400,000 900,000 400,000 900,000 900,000
3,800,000
FUNDING SCHEDULE R7000 Future Bonds R3320 State DNR/SWM
300,000
300,000 400,000 400,000 400,000 400,000 400,000
2,300,000 1,500,000
0 0 0 0
500,000
500,000 500,000
0 0 0
Total Cost:
0 300,000
300,000 400,000 900,000 400,000 900,000 900,000
3,800,000
96