Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program

Roye Williams HVAC Systemic Renovation

BOARD OF EDUCATION Project Number:

Operating Budget Impact

B204113

Council District:

F

Revenues:

Location:

Havre de Grace

Expenditures: Cost Savings: None:

Est. Debt Service:

$141,603 (annual)

X

Expended/Encumbered as of 1/9/23: $6,743,000

Project Schedule/Status:

PROJECT DESCRIPTION: This project was for the replacement and upgrade of the building's HVAC system as well as the replacement of existing plumbing piping and select plumbing fixture replacement.

EXPENDITURE SCHEDULE

Approp Total

Cost Element

Prior

FY 2024

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

890,000

890,000

890,000

0

0

Construction

10,680,000

10,680,000

10,680,000

Inspection Fees

150,000

150,000

150,000

Equipment/Furnishing

0

0

Total Cost:

11,720,000

0 11,720,000

0

0

0

0

0 11,720,000

FUNDING SCHEDULE

R7100 Prior Bonds R7920 State Bonds

6,743,000 4,977,000

6,743,000 4,977,000

6,743,000 4,977,000

0 0 0

0 0 0

Total Cost:

11,720,000

0 11,720,000

0

0

0

0

0 11,720,000