Highways Facilities Repair Program

HIGHWAYS - MISCELLANEOUS Project Number: H034506 Council District: Multiple Location: Various Est. Debt Service: $8,820

Operating Budget Impact

Revenues:

Expenditures: Cost Savings: None:

(annual)

X

Expended/Encumbered as of 1/9/23: $1,117,758

Project Schedule/Status: This is an ongoing program.

PROJECT DESCRIPTION: This project will allow for an umbrella facilities repair and improvement fund for the County Highways buildings. The program would allow for the timely repair/replacement of deteriorating roofs, parking lots, HVAC equipment, windows, salt domes and other building structures.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2024 Approp Total

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

179,000

5,000

184,000

5,000

5,000

5,000

5,000

5,000

209,000

1,184,200

1,184,200

1,184,200

Construction

158,800

90,000

248,800 10,000

90,000

90,000

90,000

90,000

90,000

698,800 35,000

Inspection Fees

5,000

5,000

5,000

5,000

5,000

5,000

5,000

Equipment/Furnishing

0

0

Total Cost:

1,527,000 100,000 1,627,000 100,000 100,000 100,000 100,000 100,000

2,127,000

FUNDING SCHEDULE

R8750 Paygo R7100 Prior Bonds R7000 Future Bonds

1,107,000 100,000 1,207,000 100,000 100,000 100,000 100,000 100,000

1,707,000

420,000

420,000

420,000

0 0 0

0 0 0

Total Cost:

1,527,000 100,000 1,627,000 100,000 100,000 100,000 100,000 100,000