Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Abingdon Park Water Main
WATER Project Number: Council District:
Operating Budget Impact
W235401
A
Revenues:
Location:
Abingdon
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 1/9/23: $0
Project Schedule/Status: Currently under design with developer CY 23: Construction anticipated
PROJECT DESCRIPTION: This project provides the funding for the County cost share to increase the size of the developer built 16" diameter water transmission main serving the proposed Abingdon Business Park to meet other system demands. The project will increase the size of 8,806 feet of water main on Edgewood Road from a 16" to 24" diameter main and increase the size of 1,145 feet of water main in Abingdon Road from a 16" to 30" diameter main.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
1,000,000 500,000 1,500,000
1,500,000
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
Total Cost:
1,000,000 500,000 1,500,000
0
0
0
0
0
1,500,000
FUNDING SCHEDULE
R8750 Paygo
1,000,000 500,000 1,500,000
1,500,000
0 0 0 0
0 0 0 0
Total Cost:
1,000,000 500,000 1,500,000
0
0
0
0
0
1,500,000