Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program

Havre de Grace Water Treatment Plant Upgrade

WATER Project Number: Council District:

Operating Budget Impact

W196141

F

Revenues:

Location:

Havre de Grace

Expenditures: Cost Savings: None:

Est. Debt Service:

$24,150 (annual)

X

Expended/Encumbered as of 1/9/23: $20,728

Project Schedule/Status: CY 2023 - Modifications to the solids handling piping. CY 2023 - Modifications to electrical system metering at the solids handling facility. Design is complete; construction anticipated for 2023

PROJECT DESCRIPTION: This project shall allow for plant improvements required throughout the plant due to technology and regulatory requirements, in addition to aging equipment.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2024 Approp Total

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

150,000

150,000

800,000

950,000

0

0

Construction

1,000,000

1,000,000

1,000,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

1,150,000

0 1,150,000

0

0

0

0 800,000

1,950,000

FUNDING SCHEDULE

R7100 Prior Bonds R8750 Paygo

1,150,000

1,150,000

1,150,000

0 0 0 0

800,000

800,000

0 0 0

Total Cost:

1,150,000

0 1,150,000

0

0

0

0 800,000

1,950,000