Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program
Bynum Ridge Replacement Sewer
SEWER Project Number: Council District:
Operating Budget Impact
S156010
D
Revenues:
Location:
Rock Spring
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 1/9/23: $639,972
Project Schedule/Status: Close project in FY24 and reallocate funds to Future Petition Projects (S215403)
PROJECT DESCRIPTION: This project is located in the Bynum Ridge subdivision adjacent to Bowles Terrace and consists of two phases. This project will cover the County's 60% reimbursement portion of Phase 1 and 100% surcharge portion for Phase II for replacement of the existing line. The cost of the project for increase in capacity is the Developer's responsibility and is in accordance with the Rules and Regulations. Phase 1 consists of approximately 835' of 15 inch sewer which replaces the 12 inch sewer between lots 16 to 20 and 28 to 33, built under contract 6010. Phase 2 consists of approximately 795' of 15 inch sewer which replaces the 12 inch sewer between lots 13 to 16 and 20 to 27, built under contract 6010.
Funds reallocated to Future Petition Projects.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2024 Approp Total
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029
TOTAL
Engineering/Design Land Acquisition
40,000
40,000
40,000
0
0
Construction
760,000 (160,028)
599,972
599,972
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
800,000 (160,028)
639,972
0
0
0
0
0
639,972
FUNDING SCHEDULE
R8751 Prior Paygo
800,000 (160,028)
639,972
639,972
0 0 0 0
0 0 0 0
Total Cost:
800,000 (160,028)
639,972
0
0
0
0
0
639,972