FY 25 Harford County Approved Capital Budget
Heavenly Waters Park - Soma 16
PARKS AND RECREATION Project Number:
Operating Budget Impact
P164116
Council District:
B
Revenues:
Location:
Benson
Expenditures: Cost Savings: None:
Est. Debt Service:
N/A
(annual)
X
Expended/Encumbered as of 1/9/23: $99,790
Project Schedule/Status: This project will be closed and remaining funds will be reappropriated to the new Heavenly Waters Park Soma Capital Project.
PROJECT DESCRIPTION: This project proposes the development of a passive park on the Soma area of Heavenly Waters Park. The County completed the repurchase of 25 acres on the site. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.
FY 25 - Paygo and Recordation Tax funding will be reappropriated to the New Heavenly Waters Park Soma Capital Project.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
200,000 (200,000)
0 0
0 0
Construction
95,000
(210)
94,790
94,790
Inspection Fees
5,000
5,000
5,000
Equipment/Furnishing
0
0
Total Cost:
300,000 (200,210)
99,790
0
0
0
0
0
99,790
FUNDING SCHEDULE R8750 Paygo R1515 Recordation Tax R8751 Prior Paygo
100,000
100,000
100,000
200,000 (200,000)
0
0
(210)
(210)
(210)
0 0
0 0
Total Cost:
300,000 (200,210)
99,790
0
0
0
0
0
99,790