FY 25 Harford County Approved Capital Budget
Joppatowne Community Center
PARKS AND RECREATION Project Number:
Operating Budget Impact
P234126
Council District:
A
Revenues:
Location:
Joppatowne
Expenditures: Cost Savings: None:
X
Est. Debt Service:
$36,000 (annual)
Expended/Encumbered as of 2/22/24: $15,000
Project Schedule/Status: FY 24: Land Acquisition FY 25-29: Engineering & Construction
PROJECT DESCRIPTION: This project will provide funding for a multipurpose center to serve leisure needs for all ages in the Joppa/Joppatowne community. The center will be utilized by the Office on Aging as a Senior Center and by the Department of Parks and Recreation for a variety of community recreation activities. Engineering and design for the project is scheduled to begin in FY 2025. Population growth will generate demand for additional recreation facilities. This project supports the goals and objectives of the 2022 Land Preservation Parks and Recreation Plan and its Capital Improvement Program recommendations.
Amended per Amendment #49 and Memorandum of Change #1
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
500,000
500,000
500,000
0
0
Construction
1,000,000 1,000,000 9,000,000
10,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
500,000 1,000,000 1,500,000 9,000,000
0
0
0
0 10,500,000
FUNDING SCHEDULE
R7100 Prior Bonds R7000 Future Bonds
500,000
500,000
500,000
1,000,000 1,000,000 9,000,000
10,000,000
0 0 0
0 0 0
Total Cost:
500,000 1,000,000 1,500,000 9,000,000
0
0
0
0 10,500,000