FY 25 Harford County Approved Capital Budget
SWM Pond Repair and Renovation
PARKS AND RECREATION Project Number:
Operating Budget Impact
P144127 Multiple Various
Council District:
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$0
(annual)
X
Expended/Encumbered as of 2/22/24: $710,288
Project Schedule/Status:
PROJECT DESCRIPTION: This project proposes the repair and renovation of existing stormwater management facilities at park sites throughout the County on an as needed basis. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program recommendations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0
0 0
Construction
1,025,000 150,000 1,175,000
150,000
150,000
1,475,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
1,025,000 150,000 1,175,000
0 150,000
0 150,000
0
1,475,000
FUNDING SCHEDULE R1515 Recordation Tax
1,025,000 150,000 1,175,000
150,000
150,000
1,475,000
0 0 0 0
0 0 0 0
Total Cost:
1,025,000 150,000 1,175,000
0 150,000
0 150,000
0
1,475,000
214