FY 25 Harford County Approved Capital Budget

Flying Point Park Improvements

PARKS AND RECREATION Project Number:

Operating Budget Impact

P164114

Council District:

A

Revenues:

Location:

Edgewood

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 2/22/24: $982,806

Project Schedule/Status: Renovation of the office/bathroom building is underway.

PROJECT DESCRIPTION: This project proposes renovations to the park amenities at Flying Point Park. Previous work was completed on the boat launch. This project supports the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

60,000

60,000

60,000

0

0

Construction

979,000 14,000

979,000 150,000

200,000

1,329,000

Inspection Fees

14,000

14,000

Equipment/Furnishing

0

0

Total Cost:

1,053,000

0 1,053,000 150,000

0

0

0 200,000

1,403,000

FUNDING SCHEDULE R1515 Recordation Tax R3399 State Other R3380 Prog. Open Sp.

455,000 198,000 400,000

455,000 150,000

200,000

805,000 198,000 400,000

198,000 400,000

0 0

0 0

Total Cost:

1,053,000

0 1,053,000 150,000

0

0

0 200,000

1,403,000