FY 25 Harford County Approved Capital Budget

Outdoor AED Construction

PARKS AND RECREATION Project Number:

Operating Budget Impact

P234127 Multiple Various

Council District:

Revenues:

Location:

Expenditures: Cost Savings: None:

Est. Debt Service:

N/A

(annual)

X

Expended/Encumbered as of 2/22/24: $4,381

Project Schedule/Status: Construction and installation of outdoor AED boxes.

PROJECT DESCRIPTION: This project proposes installation of outdoor AED machines at various County park sites. Funding from this account will be used to provide, serve, and where necessary, support small structures for outdoor AED boxes and machines. Parks and Recreation, working with the Department of Emergency Services, has installed several outdoor AED machines at park sites to date. These machines are secure and when an emergency occurs, the Emergency Operations Center provides the necessary code to open the box and access the AED. This project supports the goals and objectives of the 2022 Land Preservations, Parks and Recreation Plan and its Capital Improvement Program recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

0 0

0 0

Construction

60,000

60,000

30,000

30,000

30,000

50,000

50,000

250,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

60,000

0

60,000

30,000

30,000

30,000

50,000

50,000

250,000

FUNDING SCHEDULE R1515 Recordation Tax

60,000

60,000

30,000

30,000

30,000

50,000

50,000

250,000

0 0 0 0

0 0 0 0

Total Cost:

60,000

0

60,000

30,000

30,000

30,000

50,000

50,000

250,000