FY 25 Harford County Approved Capital Budget

Churchville Complex Development

PARKS AND RECREATION Project Number:

Operating Budget Impact

P054115

Council District:

E

Revenues:

Location:

Churchville

Expenditures: Cost Savings: None:

Est. Debt Service:

$172,244 (annual)

X

Expended/Encumbered as of 2/22/24: $8,020,884

Project Schedule/Status: FY 24: Repairs to the roof of the recreation center.

PROJECT DESCRIPTION: This project proposes the further development of the Churchville Recreation Complex. This facility houses a variety of programs for the Churchville Recreation Council. Future projects will be addressed as needs are identified. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

405,000

405,000

405,000

0

0

Construction

7,971,830

7,971,830

7,971,830

Inspection Fees

240,000

240,000

240,000

Equipment/Furnishing

0

0

Total Cost:

8,616,830

0 8,616,830

0

0

0

0

0

8,616,830

FUNDING SCHEDULE R8750 Paygo R3199 Federal Other R7100 Prior Bonds R3380 Prog. Open Space R1515 Recordation Tax

285,322 70,000

285,322 70,000

285,322 70,000

7,176,830

7,176,830

7,176,830

725,000 359,678

725,000 359,678

725,000 359,678

Total Cost:

8,616,830

0 8,616,830

0

0

0

0

0

8,616,830