FY 25 Harford County Approved Capital Budget

Intersection Improvements

HIGHWAYS - ROADS Project Number:

Operating Budget Impact

H054507 Multiple Various

Council District:

Revenues:

Location:

Expenditures: Cost Savings: None:

Est. Debt Service:

$58,440 (annual)

X

Expended/Encumbered as of 2/22/24: $3,737,440

Project Schedule/Status: FY 23: Bel Air S. Parkway and Tollgate Roundabout FY 25: Abingdon Rd & Peverly Run Rd Roundabout

PROJECT DESCRIPTION: The purpose of this project is to improve the traffic capacity and safety at selected intersections throughout the County. Reduced levels of service on most roads is a direct result of limited capacity at the intersections. Therefore, widening or redesign of the intersection under the project can result in increased capacity and safety with decreased delay. Additionally, intersections with reduced sight distance may be corrected under this project. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

397,500 115,000

20,000

417,500 115,000

20,000

20,000

20,000

20,000

20,000

517,500 115,000

Construction

4,556,728 350,000 4,906,728 350,000 350,000 350,000 350,000 350,000

6,656,728

Inspection Fees

397,500

30,000

427,500

30,000

30,000

30,000

30,000

30,000

577,500

Equipment/Furnishing

0

0

Total Cost:

5,466,728 400,000 5,866,728 400,000 400,000 400,000 400,000 400,000

7,866,728

FUNDING SCHEDULE

R8750 Paygo R6330 Developer R7100 Prior Bonds R7000 Future Bonds

3,181,728

3,181,728

3,181,728

250,000

250,000

250,000

2,035,000

2,035,000

2,035,000 2,400,000

400,000

400,000 400,000 400,000 400,000 400,000 400,000

0

0

Total Cost:

5,466,728 400,000 5,866,728 400,000 400,000 400,000 400,000 400,000

7,866,728