FY 25 Harford County Approved Capital Budget
Highways Facilities Repair Program
HIGHWAYS - MISCELLANEOUS Project Number: H034506 Council District: Multiple Location: Various Est. Debt Service:
Operating Budget Impact
Revenues:
Expenditures: Cost Savings: None:
$10,080 (annual)
X
Expended/Encumbered as of 2/22/24: $1,512,269
Project Schedule/Status: This is an ongoing program. Roof projects:
FY 25 Cooptown FY 25 Whiteford FY 26 Abingdon
PROJECT DESCRIPTION: This project will allow for an umbrella facilities repair and improvement fund for the County Highways buildings. The program would allow for the timely repair/replacement of deteriorating roofs, parking lots, HVAC equipment, windows, salt domes and other building structures.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
184,000
184,000
40,000
5,000
5,000
5,000
5,000
244,000
1,184,200
1,184,200
1,184,200 1,078,800
Construction
248,800 10,000
248,800 470,000
90,000
90,000
90,000
90,000
Inspection Fees
10,000
40,000
5,000
5,000
5,000
5,000
70,000
Equipment/Furnishing
0
0
Total Cost:
1,627,000
0 1,627,000 550,000 100,000 100,000 100,000 100,000
2,577,000
FUNDING SCHEDULE
R8750 Paygo R7100 Prior Bonds
1,207,000
1,207,000 550,000 100,000 100,000 100,000 100,000
2,157,000
420,000
420,000
420,000
0 0 0
0 0
Total Cost:
1,627,000
0 1,627,000 550,000 100,000 100,000 100,000 100,000
2,577,000
370