FY 25 Harford County Approved Capital Budget

Abingdon WTP Switch Gear/Generator Upgrade

WATER Project Number: Council District:

Operating Budget Impact Revenues:

W205424

F

Location:

Abingdon

Expenditures: Cost Savings:

Est. Debt Service:

$147,600 (annual)

None: X

Expended/Encumbered as of 2/22/24: $295,224

Project Schedule/Status: FY24 - Preliminary Design FY25 - Complete Design FY26 - Construction

PROJECT DESCRIPTION: The electrical feed switch gear and main breaker system into the Abingdon Water Treatment Plant was recently evaluated and spare units are no longer available. A critical failure could put the plant operation in jeopardy. This project will design and build a new switch gear and back up generator system. The single new switch gear will integrate two separate electrical feeds and a back-up generator for redundancy of plant power sources, and resiliency during electrical interruptions.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

150,000 300,000

450,000

450,000

0

0

Construction

6,000,000

6,000,000 5,000,000

11,000,000

Inspection Fees

0 500,000

500,000

Equipment/Furnishing

0

0

Total Cost:

6,150,000 300,000 6,450,000 5,500,000

0

0

0

0 11,950,000

FUNDING SCHEDULE

6,150,000

6,150,000

6,150,000 5,500,000

R7100 Prior Bonds R7000 Future Bonds R8750 Paygo

0 5,500,000

300,000

300,000

300,000

0 0

0 0

Total Cost:

6,150,000 300,000 6,450,000 5,500,000

0

0

0

0 11,950,000