Replacement of Water Booster Station SCADA

WATER Project Number: Council District:

Operating Budget Impact Revenues:

W156492 Multiple Abingdon

Location:

Expenditures: Cost Savings:

Est. Debt Service:

$46,800 (annual)

None: X

Expended/Encumbered as of 2/22/24: $2,569,348

Project Schedule/Status: FY24 - Phase 2 replacements FY24 - 25 - Phase 3 replacements

PROJECT DESCRIPTION: This project will allow for a study to select the appropriate replacement system for Water Booster Station Supervisory Control and Data Acquisition (SCADA) system. The project will allow for the design and performance specifications to be developed and installed. The existing SCADA equipment is obsolete and parts are not manufactured anymore and Siemens does not support the system equipment. Project work will proceed phase-wise, based on evaluation and on-call professional advisement. It will include replacement and/or upgrade of all the distribution system's RTUs

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2025 Approp Total

FY 2026 FY 2027 FY 2028 FY 2029 FY 2030

TOTAL

Engineering/Design Land Acquisition

300,000

300,000

300,000

0

0

Construction

2,950,000 700,000 3,650,000

3,650,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

3,250,000 700,000 3,950,000

0

0

0

0

0

3,950,000

FUNDING SCHEDULE

1,950,000

1,950,000

1,950,000 2,000,000

R7100 Prior Bonds

R8750 Paygo

1,300,000 700,000 2,000,000

0 0 0

0 0 0

Total Cost:

3,250,000 700,000 3,950,000