FY 25 Harford County Approved Capital Budget
Water & Sewer Infrastructure Improvements Projects
WATER Project Number: Council District:
Operating Budget Impact Revenues:
W196150 Multiple
Location:
Various
Expenditures: Cost Savings:
Est. Debt Service:
$0
(annual)
None: X
Expended/Encumbered as of 2/22/24: $413,393
Project Schedule/Status: FY24 - Harford Square Design FY25 - Harford Square Construction
PROJECT DESCRIPTION: This project will identify and implement infrastructure improvement projects with the activities of studying, modeling, evaluation, master planning, designing and construction. This project will also include improvements to water & sewer plants and facilities. Funds reallocated from City of Baltimore Raw Water Supply (W126719) @ $78,461 Project work includes: Harford Square water and sewer extensions; Grace Hall water booster station; Capital connection charge for future raw water capacity increase from City of Baltimore; Septage receiving facility upgrade at Sod Run WWTP.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
2,341,340 (1,000,000)
1,341,340
1,341,340
0
0
Construction
150,000 2,080,000 2,230,000 1,000,000 1,000,000 1,000,000 1,000,000
6,230,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
2,491,340 1,080,000 3,571,340 1,000,000 1,000,000 1,000,000 1,000,000
0
7,571,340
FUNDING SCHEDULE
2,191,340 1,080,000 3,271,340 1,000,000 1,000,000 1,000,000 1,000,000
7,271,340
R8750 Paygo
R6330 Developer
300,000
300,000
300,000
0 0 0
0 0 0
Total Cost:
2,491,340 1,080,000 3,571,340 1,000,000 1,000,000 1,000,000 1,000,000
0
7,571,340
383