FY 25 Harford County Approved Capital Budget
Perryman Wellfield Improvements
WATER Project Number: Council District:
Operating Budget Impact Revenues:
W186056
F
Location:
Perryman
Expenditures: Cost Savings:
Est. Debt Service:
$3,600
(annual)
None: X
Expended/Encumbered as of 2/22/24: $0
Project Schedule/Status: FY25 - Design scope development
PROJECT DESCRIPTION: This project allows for improvements to the wellhouses in the Perryman well system since the wellhouses are reaching the end of their economic life. The upgrades needed for the wellhouses includes a new roof, HVAC, controls, materials, and emergency power backup.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
350,000
350,000
350,000
0 0 0 0
0
Construction
3,500,000
3,500,000
Inspection Fees
0 0
Equipment/Furnishing
Total Cost:
350,000
0
350,000
0 3,500,000
0
0
0
3,850,000
FUNDING SCHEDULE
200,000 150,000
200,000 150,000
200,000 150,000
R8750 Paygo
R7100 Prior Bonds R7000 Future Bonds
0 0 0
3,500,000
3,500,000
0 0
Total Cost:
350,000
0
350,000
0 3,500,000
0
0
0
3,850,000
391