FY 23 APPROVED CAPITAL BUDGET
Stafford Road Bridge #162
HIGHWAYS - BRIDGES Project Number:
Operating Budget Impact
H234504
Council District:
D
Revenues:
Location:
Darlington
Expenditures: Cost Savings: None:
Est. Debt Service:
$2,000
(annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: FY 23-24: Design FY 25: Right of way/permits FY 27: Construction
PROJECT DESCRIPTION: This bridge carries Stafford Road over Buck Branch and has a deteriorated deck and beams. The project is planned to replace the bridge superstructure and upgrade the abutments. The project is eligible for Federal funding. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
400,000
400,000 400,000
800,000 25,000 900,000 100,000
0 0 0 0
25,000
Construction
900,000 100,000
Inspection Fees
Equipment/Furnishing
0
Total Cost:
0 400,000
400,000 400,000
25,000
0 1,000,000
0
1,825,000
FUNDING SCHEDULE
R3140 Federal TAP R7000 Future Bonds
320,000 80,000
320,000 320,000
800,000 200,000
1,440,000
80,000
80,000
25,000
385,000
0 0 0
0 0 0
Total Cost:
0 400,000
400,000 400,000
25,000
0 1,000,000
0
1,825,000