FY 23 APPROVED CAPITAL BUDGET
Fallston Area Sewer
SEWER Project Number: Council District:
Operating Budget Impact
S196165 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$95,000 (annual)
X
Expended/Encumbered as of 2/9/22: $0
Project Schedule/Status: Study/evaluation is complete. Engineering and design in future years.
PROJECT DESCRIPTION: This project includes design and construction for rehabilitation of existing sewer mains and pumping stations as defined in the Fallston Sewer Capacity Study. The upgrades to the mains and pumping stations are required to serve future growth.
EXPENDITURE SCHEDULE
Approp Total
Cost Element
Prior
FY 2023
FY 2024 FY 2025 FY 2026 FY 2027 FY 2028
TOTAL
Engineering/Design Land Acquisition
425,000
425,000
425,000
0
0
Construction
3,375,000
3,375,000
3,375,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
3,800,000
0 3,800,000
0
0
0
0
0
3,800,000
FUNDING SCHEDULE
R7100 Prior Bonds
3,800,000
3,800,000
3,800,000
0 0 0 0
0 0 0 0
Total Cost:
3,800,000
0 3,800,000
0
0
0
0
0
3,800,000
406
Made with FlippingBook Online newsletter creator