FY 25 Harford County Approved Capital Budget
Facility Repair/Life-Cycle Program
GENERAL Project Number: Council District:
Operating Budget Impact
A234105 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
$168,011 (annual)
X
Expended/Encumbered as of 2/22/24: $2,364,995
Project Schedule/Status:
FY25: Highland Center replace the lower roof and repoint area between the two roofs, Office of Aging replace the boiler and HVAC system, 212 S. Bond St. replace the HVAC System, Roni Chenowith Center replace the roof top units (RTU), Comprehensive Facility Condition Assessment (FAC), Replace Transit fire alarm system.
PROJECT DESCRIPTION: This project provides funding for the replacement, renovation, and repairs of county building systems (site, roofing, structural, exterior, interior, mechanical, plumbing, electrical, fire/life safety, and conveyances). DPW Facilities & Operations will oversee and manage this project.
Amended per Amendment #43
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
410,000 1,500,000 1,910,000 1,500,000 1,500,000 1,500,000 1,500,000 1,500,000
9,410,000
0
0
Construction
4,790,000 500,460 5,290,460 500,000 500,000 500,000 500,000 500,000
7,790,460
Inspection Fees
0 0
0
Equipment/Furnishing
0 5,200,000 2,000,460 7,200,460 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 17,200,460
Total Cost:
FUNDING SCHEDULE R7000 Future Bonds R7100 Prior Bonds R3199 Federal Other R6130 Invest. Income
2,000,460 2,000,460 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 12,000,460
5,000,000
5,000,000
5,000,000
200,000
200,000
200,000
0 0
0
0 5,200,000 2,000,460 7,200,460 2,000,000 2,000,000 2,000,000 2,000,000 2,000,000 17,200,460
Total Cost: