FY 25 Harford County Approved Capital Budget
Fleet Replacement
GENERAL Project Number: Council District:
Operating Budget Impact
A124102 Multiple Various
Revenues:
Location:
Expenditures: Cost Savings: None:
Est. Debt Service:
N/A
(annual)
X
Expended/Encumbered as of 2/22/24: $21,410,646
Project Schedule/Status: This project is ongoing.
PROJECT DESCRIPTION: This project will provide funds for the replacement of essential vehicles and equipment to enable agencies to perform their critical jobs in county government. Units to be replaced are on average 10 years old with high mileage and have become unreliable.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
0 0 0 0
0 0 0 0
Construction
Inspection Fees
Equipment/Furnishing
23,965,000 1,000,000 24,965,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 29,965,000 23,965,000 1,000,000 24,965,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 29,965,000
Total Cost:
FUNDING SCHEDULE R8750 Paygo R6130 Invest. Income
21,065,000
21,065,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 26,065,000
2,900,000 1,000,000 3,900,000
3,900,000
0 0 0
0 0
0 23,965,000 1,000,000 24,965,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 29,965,000
Total Cost:
75