FY 27 Proposed Capital Budget
St. Clair Bridge Road Bridge #100
HIGHWAYS - BRIDGES Project Number:
Expended/Encumbered as of 2/3/26: $62,364
H254501
Council District:
D
Location:
Street
Project Schedule/Status: FY 25-28: Design FY 29: Right of Way/ Permits/ Utility FY 30/31: Construction
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project is to replace the deck and rehabilitate remaining bridge elements on the St. Clair Bridge Road over Deer Creek. The current bridge is listed in fair condition. This project is eligible for Federal aid funding. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
400,000 400,000
800,000
800,000 50,000
0 0 0 0
50,000
Construction
950,000 950,000
1,900,000
Inspection Fees
50,000
50,000
100,000
Equipment/Furnishing
0
Total Cost:
400,000 400,000
800,000
0
50,000 1,000,000 1,000,000
0
2,850,000
FUNDING SCHEDULE
R3140 Federal TAP R7100 Prior Bonds R7000 Future Bonds
320,000 320,000
640,000 80,000 80,000
800,000 800,000
2,240,000
80,000
80,000 530,000
80,000
50,000 200,000 200,000
Total Cost:
400,000 400,000
800,000
0
50,000 1,000,000 1,000,000
0
2,850,000
Estimated Debt Service ESTIMATED OPERATING BUDGET IMPACT:
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL 14,028
2,672
2,538
2,405
2,271
2,138
2,004
283