FY 27 Proposed Capital Budget
Bridge Painting
HIGHWAYS - BRIDGES Project Number:
Expended/Encumbered as of 2/3/26: $889,257
H144501 Multiple Various
Council District:
Location:
Project Schedule/Status: Various projects are continuously being designed and constructed under this account.
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project provides funding to paint bridges in Harford County. This preventative maintenance project will help to conserve future County resources by extending the life of the existing bridges and forestalling expensive replacement costs. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031
FY 2032
TOTAL
Engineering/Design Land Acquisition
55,000
55,000
20,000
20,000
20,000
20,000 135,000
0
0
Construction
1,725,000
1,725,000 440,000 440,000
440,000 40,000
440,000 3,485,000 40,000 330,000
Inspection Fees
170,000
170,000
40,000
40,000
Equipment/Furnishing
0
0
Total Cost:
1,950,000
0 1,950,000 500,000 500,000
0 500,000
500,000 3,950,000
FUNDING SCHEDULE
950,000
950,000 500,000 500,000
0 500,000
500,000 2,950,000
R8750 Paygo R3140 Federal TAP
1,000,000
1,000,000
1,000,000
0 0 0
0 0 0
Total Cost:
1,950,000
0 1,950,000 500,000 500,000
0 500,000
500,000 3,950,000
ESTIMATED OPERATING BUDGET IMPACT:
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031
FY 2032
TOTAL
289
Made with FlippingBook Ebook Creator