FY 27 Proposed Capital Budget

Old Pylesville Road Bridge #138

HIGHWAYS - BRIDGES Project Number:

Expended/Encumbered as of 2/3/26: $322,021

H264503

Council District:

D

Location:

Pylesville

Project Schedule/Status: FY 26: Design FY 28: Right of Way/ Permits/ Utility FY 30: Construction

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project will replace the existing bridge on Old Pylesville Road over Jacks Hole stream. The current structure is a poor rated structure with both the deck and supestructure in poor condition. Replacement of the bridge will remove a poor rated bridge from the County inventory.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2027 Approp Total

FY 2028 FY 2029 FY 2030 FY 2031

FY 2032

TOTAL

Engineering/Design Land Acquisition

400,000

400,000

400,000 25,000 900,000 100,000

0 0 0 0

25,000

Construction

900,000 100,000

Inspection Fees

Equipment/Furnishing

0

Total Cost:

400,000

0

400,000

25,000

0 1,000,000

0

0 1,425,000

FUNDING SCHEDULE

R7000 Future Bonds R7100 Prior Bonds

400,000

0

400,000

400,000

0 0 0 0

25,000

1,000,000

1,025,000

0 0 0

0 0

0

Total Cost:

400,000

0

400,000

0

0

0

0 1,425,000

Estimated Debt Service ESTIMATED OPERATING BUDGET IMPACT:

FY 2027 13,360

FY 2028 FY 2029 FY 2030 FY 2031

FY 2032 10,020

TOTAL 70,140