FY 27 Proposed Capital Budget

Tollgate Road Culvert Replacement

HIGHWAYS - BRIDGES Project Number:

Expended/Encumbered as of 2/3/26: $0

H264504

B

Council District:

Bel Air

Location:

Project Schedule/Status: FY 25-27: Design FY 27/28: Right of way/ Permits/ Utility FY 29: Construction

Expended/Enc.

Budget

PROJECT DESCRIPTION: This culvert carries Tollgate Road over Tributary to Winters Run, adjacent to Winters Run Country Club. Culvert was subject to damage during a flood event in January 2024, which created roadway cracks and embankment stability issues with the adjcent roadway slopes. Design is to replace culvert with a larger facility to pass larger design storms as well as improve this section of Tollgate Road. This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2027 Approp Total

FY 2028 FY 2029 FY 2030 FY 2031

FY 2032

TOTAL

Engineering/Design Land Acquisition

25,000 25,000

25,000 25,000

25,000 25,000

Construction

0 2,400,000 2,400,000 0 100,000 100,000

4,800,000

Inspection Fees

200,000

Equipment/Furnishing

0

0

Total Cost:

50,000

0

50,000 2,500,000 2,500,000

0

0

0 5,050,000

FUNDING SCHEDULE

R7000 Future Bonds R7100 Prior Bonds

50,000

50,000

50,000

0 2,500,000 2,500,000

5,000,000

Total Cost:

50,000

0

50,000 2,500,000 2,500,000

0

0

0 5,050,000

FY 2027

FY 2028 FY 2029 FY 2030 FY 2031

FY 2032

TOTAL 8,768

Estimated Debt Service ESTIMATED OPERATING BUDGET IMPACT:

1,670

1,587

1,503

1,420

1,336

1,253

300

Made with FlippingBook Ebook Creator