FY 27 Proposed Capital Budget
Spesutia Road Reconstruction/Upgrade
HIGHWAYS - ROADS Project Number:
Expended/Encumbered as of 2/3/26: $643,336
H194508
Council District:
F
Location:
Perryman
Project Schedule/Status: FY 19: Preliminary Analysis/Design FY 20: Right of Way acquisition FY 22: Construction
Expended/Enc.
Budget
PROJECT DESCRIPTION: This project consists of improving Spesutia Road between US40 and MD 159 to address safety and traffic volume increases due to the continuous and ongoing development in the Perryman peninsula area. Approximately 4,000 linear feet of closed section road is proposed to be built. Spesutia Road functions as a collector road between two State roads. The improvements are proposed to include capacity upgrades at the two State road intersections as well as road widening to accommodate a bicycle shoulder/lane and sidewalks where necessary.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2025 Approp Total
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
TOTAL
Engineering/Design Land Acquisition
500,000 250,000
500,000 250,000
500,000 250,000
Construction
5,000,000
5,000,000
5,000,000
Inspection Fees
0 0
0 0
Equipment/Furnishing
Total Cost:
5,750,000
0 5,750,000
0
0
0
0
0
5,750,000
FUNDING SCHEDULE
R8750 Paygo R7100 Prior Bonds
500,000
500,000
500,000
5,250,000
5,250,000
5,250,000
0 0 0
0 0 0
Total Cost:
5,750,000
0 5,750,000
0
0
0
0
0
5,750,000
331