FY 27 Proposed Capital Budget
Roadway Rehabilitation
HIGHWAYS - RESURFACING Project Number: New Council District: Multiple Location: Various Project Schedule/Status: Various projects are continuously being designed and constructed under this account.
Expended/Encumbered $0
Expended/Enc.
Budget
PROJECT DESCRIPTION: This is an ongoing maintenace activity to repair the County's 700+ miles of asphalt pavement. This maintenance program includes asphalt patching on various roadways to address pavement failures and includes using a polymer modified asphalt paving on various roadways to address settlement of pavement around manholes, water valves and bridge approaches.
This project is consistent with the Master Planning goal of maintaining a safe and adequate transportation system to serve existing and future populations.
EXPENDITURE SCHEDULE
Cost Element
Prior
FY 2027 Approp Total
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
Engineering/Design Land Acquisition
15,000
15,000
15,000
15,000
15,000
15,000
15,000
90,000
0
0
Construction
450,000 35,000
450,000 450,000 450,000 450,000 450,000 450,000
2,700,000
Inspection Fees
35,000
35,000
35,000
35,000
35,000
35,000
210,000
Equipment/Furnishing
0
0
Total Cost:
0 500,000
500,000 500,000 500,000 500,000 500,000 500,000
3,000,000
FUNDING SCHEDULE
R8750 Paygo R7000 Future Bonds
500,000
500,000 500,000 500,000 500,000 500,000 500,000
3,000,000
0 0 0 0
0 0 0 0
Total Cost:
0 500,000
500,000 500,000 500,000 500,000 500,000 500,000
3,000,000
ESTIMATED OPERATING BUDGET IMPACT:
FY 2027
FY 2028 FY 2029 FY 2030 FY 2031 FY 2032
TOTAL
337