Harford County, MD FY 24 Proposed Capital Budget & Capital Improvement Program

Streetlights

HIGHWAYS - ROADS Project Number:

Operating Budget Impact

H234503 Multiple Various

Council District:

Revenues:

Location:

Expenditures: Cost Savings: None:

Est. Debt Service:

$0

(annual)

X

Expended/Encumbered as of 1/9/23: $49,700

Project Schedule/Status: Schedule to be determined.

PROJECT DESCRIPTION: This project provides for the upgrading of County owned streetlights. This consists of the complete replacement of streetlights and/or the replacement of the lighting to LED. The replacement of these lighting fixtures will result in monthly energy savings. This project will also include repairs to existing streetlights.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2024 Approp Total

FY 2025 FY 2026 FY 2027 FY 2028 FY 2029

TOTAL

Engineering/Design Land Acquisition

5,000

10,000

15,000

10,000

10,000

10,000

10,000

10,000

65,000

0

0

Construction

45,000

90,000

135,000

90,000

90,000

90,000

90,000

90,000

585,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

50,000 100,000

150,000 100,000 100,000 100,000 100,000 100,000

650,000

FUNDING SCHEDULE

R8750 Paygo

50,000 100,000

150,000 100,000 100,000 100,000 100,000 100,000

650,000

0 0 0 0

0 0 0 0

Total Cost:

50,000 100,000

150,000 100,000 100,000 100,000 100,000 100,000

650,000