FY 27 Proposed Capital Budget

Bush River Dredging and DMP Site

PARKS AND RECREATION Project Number: New Council District:

Expended/Encumbered $0

Multiple Abingdon

Location:

Project Schedule/Status: FY 27: Engineering

Expended/Enc.

Budget

PROJECT DESCRIPTION: This project includes remediation of the Dredge Material Placement (DMP) site at Perryman Park on Fords Lane. Prior funding was used for engineering to determine the need for future dredging. A large portion of the project will be funded by the Department of Natural Resources (DNR), Waterway Improvement Program. This project supports the goals and objectives of the 2022 Land Preservation, Parks and Recreation Plan and its Capital Improvement Program Recommendations.

EXPENDITURE SCHEDULE

Cost Element

Prior

FY 2027 Approp Total

FY 2028 FY 2029 FY 2030 FY 2031 FY 2032

TOTAL

Engineering/Design Land Acquisition

0 0

75,000

75,000

0

Construction

0 775,000

775,000

Inspection Fees

0 0

0 0

Equipment/Furnishing

Total Cost:

0

0

0 850,000

0

0

0

0

850,000

FUNDING SCHEDULE R1515 Recordation Tax R3399 State Other

0

50,000

50,000 800,000

0 800,000

0 0 0

0 0 0

Total Cost:

0

0

0 850,000

0

0

0

0

850,000

ESTIMATED OPERATING BUDGET IMPACT:

FY 2027

FY 2028 FY 2029 FY 2030 FY 2031 FY 2032

TOTAL

205